Additional information is always gratefully received, whether entirely new records (particularly historical records) or information to fill in gaps or correct errors, via the contact link under the Miscellaneous entry in the navigation bar above. Thank you.
Mileages are given in the form miles.chains unless stated otherwise. Figures prefixed with ≈ are approximate, those in parentheses are not on this route but are given for reference. Reference to 'start'/'end' of an asset are as read down the page.
Distances on this page are taken from drawings submitted to parliament in preparation for the acts permitting construction. Most are derived from scaling drawings; only a few defined points were given. All figures are in km and all are subject to change as the project progresses.
It is expected that separate ELR codes will be allocated in due course, at which point the data below will move to appropriate new pages.
HS2 main line
0.000 EUSTON
9.075 OLD OAK COMMON
148.800 Carol Green intersection bridge over RBS1 (99.30)
156.664 BIRMINGHAM INTERCHANGE
160.426 Fordbridge Junction (up line) with Birmingham spur
160.453 Fordbridge Junction (down line) with Birmingham spur
165.345 Hams Hall Junction with North Chord (0.000) and Leeds spur (0.000)
192.949 Handsacre Junction with LEC2 (mean) (mileage unknown)
HS2 Birmingham spur
160.426 Fordbridge Junction (up line) with main line
160.453 Fordbridge Junction (down line) with main line
164.529 Castle Bromwich Junction (down line) with north chord (4.394)
164.612 Castle Bromwich Junction (up line) with north chord (3.280)
175.654 BIRMINGHAM CURZON STREET
HS2 Leeds spur
0.000 Hams Hall Junction with main line (165.345)
2.141 end of phase 1 construction (down line)
4.391 end of phase 1 construction (up line)
HS2 north chord
0.000 Hams Hall Junction with main line (165.345)
3.280 Castle Bromwich Junction (down line) with Birmingham spur (164.612)
4.394 Castle Bromwich Junction (up line) with Birmingham spur (164.529)